The purpose of this procedure is to provide a mechanism to perform the topography line survey to ensure its continuing suitability and effectiveness.
2 SCOPE
The scope of this process covers all aspects with line survey, including polygon/traverse, staking, clearing, bridging, data processing and report.
3 INTERFACE DOCUMENTS
Interface documents are defined as MS documents that have direct links; either by reference, input or output. Interface documents with this Management Procedure are:
3.1 Level 1 – Management Manual Interfaces
- MM.001 Management Manual
- MM.002 QHSE Policy
3.2 level 2 – procedure interfaces
- SMC.022 Chaining & Flagging
- SMC.023 Clearing & Bridging
- SMC.024 GPS Static Survey
- SMC.025 Line Survey Processing
- SMC.026 GPS Static Survey processing
3.3 level 3 – form. record & WI interfaces
- FM.SMC.011 List of Topography Equipment
- FM.SMC.012 Instrument Check (Check of Distance)
- FM.SMC.013 Instrument Check (Check of Angle)
- FM.SMC.014 Line Survey Instruction
- FM.SMC.015 Report by Radio
- FM.SMC.016 Raw Data File
- FM.SMC.017 Bridging Order
- FM.SMC.018 Clearing and Bridging Report
- FM.SMC.019 Line Sketch
- FM.SMC.020 Bench Mark Sketch Location
- FM.IMS.OO4. Document retention and archive periods
4 PROCEDURE
4.1 Method
The method shown in the following flow chart identifies the process activities and controls. The notes provided herein give clarification and expand the detail explanation of the flow chart.
|
Final Report |
|
Actual Coordinate: Line (TR & SP) and Benchmark, Position and Base Map |
|
Procedure, Production Quantity and Quality |
|
Suitable with Azimuth, Coordinate Control and any Deviation ? |
|
Polygon/traverse |
|
· SMC.023 |
|
· SMC.022 & WI.SMC.024 |
|
Line Survey (Staking out of Coordinate using Total Station)/RTK GPS
|
|
Clearing |
|
Hardcopy and Softcopy Data of Line Position for supporting Processing Seismology Department (SEG P1, CMB File) |
Y |
|
§ Data from Client: Line Coordinate (SPS file, Start and End Point of Line) § Base Map § Point (BM, Well) |
|
Other reference point for starting of line survey and ties |
|
· SMC.025 · WI.SMC.027 |
N |
|
Revision |
|
· WI.SMC.023 & WI.SMC.026 |
|
Bridging |
|
Field Data Processing |
|
Final Data Processing and Drafting |
|
· SMC.023 |
|
START |
|
END |
|
· FM.SMC.011,FM.SMC.012, FM.SMC.013 |
|
· FM.SMC.014 |
|
· FM.SMC.017 |
|
FM.SMC.015 & FM.SMC.016 |
|
FM.SMC.018 |
|
FM.SMC.019 & FM.SMC.020 |
|
FM.SMC.018 |
|
· Line Plan Plotting · Field Orientation · Prepare Equipment |
- Geodetic engineer complete data from client, including line coordinate, base map and reference point.
- Geodetic engineer prepare the instruments survey, plan the blocking and polygon/traverse design.
- Geodetic engineer ensure that data was suitable with azimuth, coordinate control and deviation. If data not suitable, the process back to line survey (revision).
- Geodetic engineer conduct data processing.
- Senior surveyor process data from field and make previous program of line survey.
- Senior surveyor help geodetic engineer, and conduct the polygon design, blocking and loop accuracy.
- Field surveyor performs line survey with stakeout method. Field surveyor ensures accuracy, numbering and recording of data.
- Subcontractor conducts line clearing and bridging. Field surveyor ensures that clearing comply with specification. Geodetic engineer or Senior- surveyor ensures that clearing and bridging comply with specification.
4.2 RECORDS
Records resulting from this procedure are identified in the flow chart. The retention and archive periods for records is defined in FM.IMS.004 (Document Retention & Archive Periods).